Data Center Design and Construction: Key Milestones and Project Timeline

Data center design and construction represent a complex process that requires careful planning and coordination among its diverse stages to ensure all potential dependencies are well balanced.

Starting from the first feasibility studies, moving onto the conceptual design and planning, engineering, procurement, construction, and installation, it finishes with data center commissioning and handover: an intricate process that requires experienced professionals capable of coordinating very different areas and ensuring all individual parts end up working together and in equilibrium as part of the data center.

As the advancement of efficient data centers is increasingly linked with the progress of the digital economies, a lot depends on data center facility design being successful. And projects are spreading at a rising pace: data center construction represented almost a third (32%) of office construction spending in 2024 (up from 5% in 2014) and is expected to approach 40% by 2028, according to Oxford Economics.

In the meantime, all involved in these advancements are grappling with the same question: how to approach the data center construction process so that projects move on successfully while meeting (and even exceeding) all technical, economic, and regulatory requirements.

Below is a look at the typical data center construction timeline, with a particular focus on data center cooling systems and a list of challenges and best practices for data center design and construction that make a difference.

Nueva llamada a la acción

What Are the Main Phases of Data Center Design and Construction?

The following represents a typical outline of the main steps in a data center construction schedule:

Phase

What gets done

How it relates to other stages

Feasibility Study and Site Selection

Evaluation of feasibility, energy availability, connectivity, location, and project requirements

Having clear notions of the data center’s conceptual design and capacity planning can be relevant to inform the site selection process

Conceptual Design and Capacity Planning

Capacity, IT loads, electrical infrastructure, and cooling needs are defined

Parameters like energy availability and connectivity (determined in the first stage) are key to ensure the project’s capacity goals can be met

Detailed Engineering and Infrastructure Design

Engineering is developed, technologies are selected, redundancy and efficiency targets are defined, and all engineering disciplines are coordinated

Site selection choices can have an influence on this stage. For instance, space availability within the site is important for determining the available space for IT, mechanical and electrical equipment

Procurement and Equipment Manufacturing

Supplier selection, critical equipment acquisition, manufacturing and logistic planning

The goals set in stage 2 (regarding capacity, IT loads, electric infrastructure and cooling needs) should inform the choice of suppliers. Additionally, good procurement efforts facilitate moving on with realistic timelines and without delays in the construction and installation stage

Construction and Installation

Construction execution, electrical, mechanical and cooling infrastructure installation, system integration

Well-structured plans and decisions taken during previous stages are capable of either facilitating the implementation stage or generating obstacles as well as construction and installation delays and cost escalations

Testing and Commissioning

Equipment verification, functional tests, system performance validation

A correct execution of this phase is directly tied to the success of the data center’s operational readiness

Handover and Operational Readiness

Documentation handover, operator training and operational readiness

Getting to this stage without delays or cost overruns depends on the previous stages having been well structured

 

Data Center Design and Construction: Step-by-Step Timeline

Phase 1: Feasibility Study and Site Selection

The first stage largely consists of analyzing the overall project’s feasibility by establishing the following:

  • Location, a choice tightly linked to issues such as energy availability, connectivity options (often prioritizing the availability of fiber infrastructure and suitable bandwidth), proximity to end users and locations rarely affected by extreme weather. When it comes to energy availability, data centers tend to prioritze choices where power is reliably available, is cost-effective and produced sustainably.
  • Main project requirements, like potential scalability needs and regulatory needs.

These initial considerations in the data center construction timeline all serve as the foundation for the data center infrastructure design that continues on to the next stages.

Phase 2: Conceptual Design and Capacity Planning

This stage should be carefully aligned with the analysis in the first step, focusing on establishing the project’s requirements around:

  • Capacity planning, determining the project’s required electrical load in order to ensure a match with the available power at the location.
  • Expected IT loads.
  • The technical equipment capable of meeting these capacity needs and IT loads. This includes determining the required electric infrastructure and cooling solutions that will dissipate heat and ensure equipment safety and efficiency.

Along with the information gathered during the first stage, completing this second step should allow the execution of detailed cost projections (incorporating issues such as the required technical equipment, land acquisition or the expected construction expenses, among others).

Additionally, it should allow for confidently moving forward with data center design and construction choices from the technical and engineering point of view.

Phase 3: Detailed Engineering and Infrastructure Design

This third stage in the data center construction process involves matching the right data center infrastructure with the project’s goals and available resources. As such, the following aspects around data center engineering must be considered:

  • Selection of technologies, including components for servers, storage and networking systems and data center cooling infrastructure, among other elements.
  • Redundancy needs, with Uptime Institute standards being useful to size the project’s backup and resiliency needs correctly.
  • Possibilities for energy efficiency, crucial for ensuring current and future compliance with regulations, as well as from an economic and sustainability point of view. Choices around data center cooling systems can have a significant impact here, while ASHRAE guidelines offer standards for efficient data center cooling infrastructure.
  • Discipline coordination via adequate data center project management.

Phase 4: Procurement and Equipment Manufacturing

This stage follows a structured sequence that starts with supplier selection and moves on to the acquisition of technical equipment and its fabrication from the chosen suppliers. Main purchases to consider here are related to servers and racking, network and storage equipment, power supplies and data center cooling systems.

Alongside these steps, the logistical plan that informs the data center construction schedule should be outlined, considering the timelines offered by providers.

Phase 5: Construction and Installation

This stage involves the actual execution of construction works according to a realistic data center construction timeline that takes into account and gathers all the previous stages’ efforts.

Among the most important and delicate operations here is the installation of the electric, mechanical and cooling infrastructure.

Meanwhile, the correct integration of all systems should be ensured so that all parts work in alignment within the complex ecosystem that arises during data center design and construction.

Phase 6: Testing and Commissioning

The final stage before actual operation is devoted to data center commissioning: testing the equipment, executing functional tests and validating both performance and system integration to ensure the data center operates as expected.

Phase 7: Handover and Operational Readiness

After a successful launch, document handover takes place and formally signals the project turnover. This final stage in data center design and construction also comprises the required operator training processes and any other preparations needed for the data center’s successful operation.

build_data_center

How Long Does It Take to Design and Build a Data Center?

There’s no single answer to how long it takes to design and build a data center, with each project requiring a specific analysis and study to be able to determine a realistic data center construction timeline. As a reference, however, a period of around 24 months can be mentioned for a 20 MW data center construction project, assuming all processes proceed as planned.

Any figures around a data center construction schedule must necessarily consider the different factors that can have an influence on this timeline, including the projects’ size, technical needs and/or location. Industry media also point to issues like labor and equipment shortages as well as potential public opposition as capable of having an influence on data center design and construction processes.

The Role of Cooling Infrastructure in Data Center Design and Construction

Data center cooling systems are crucial for successful data center operation, and must therefore be thoroughly considered during the data center design and construction process.

Briefly put, adequate data center cooling design ensures heat produced by IT equipment is effectively removed from systems, protecting them and data center operations as a whole. This thermodynamic reality makes efficient data center cooling infrastructure a critical priority, especially in a context of increasing IT loads and rack densities.

The following three aspects can make a difference in ensuring data center cooling systems are correctly implemented:

Early Cooling System Planning and Design

Data center cooling infrastructure must be understood as a central aspect of a project’s success. In practice, this means analyzing the best cooling design choices from the early stages, rather than considering them as an add-on in later steps.

For instance, choices around what types of cooling technologies to introduce (from central cooling for hyperscale data centers to integrating data centers and district heating) benefit from early integration.

Cooling Equipment Selection, Manufacturing and Installation

Selecting the right technology (by matching it to the IT equipment’s cooling needs and the data center’s overall goals) represents the first step. After that, it’s essential to plan implementation alongside suppliers and integrate cooling systems with the rest of the infrastructure.

Cooling System Testing and Commissioning

The data center construction timeline must incorporate dedicated operational and performance testing for data center cooling infrastructure, ensuring it achieves the performance, control and redundancy goals before going live.

Common Challenges in Data Center Construction

Some of the most common causes of delay in data center construction include:

  • Limited energy availability, mainly due to potential grid issues or supply chain disruptions.
  • Equipment with long lead times on the supply end.
  • Difficulties in coordinating contractors.
  • Late-stage design revisions.
  • Frictions during commissioning processes.

A proactive approach to facing these challenges necessarily implies a combination of:

  • Project leadership by experienced professionals from a technical standpoint and accessed through rigorous supplier evaluation. Specialized knowledge in areas such as data center cooling infrastructure is crucial, while also guaranteeing an approach to data center design and construction that considers how all parts will work together as a cohesive ecosystem.
  • Careful planning (including site selection choices) and scheduling efforts by capable management.
  • Proactive procurement to avoid supply chain disruptions and other delays.

What Companies Are Involved in Data Center Design and Construction?

Data center construction companies include a wide range of specialized suppliers, from promoters to engineering consultancies, construction companies, specialized contractors and critical infrastructure providers.

In this context, ARANER operates from a unique standpoint: our expertise in thermal engineering allows us to optimize thermal performance in data centers as EPC contractors while also setting the foundations for efficient operation through seamless data center design and construction processes.

Download our Data Center Whitepaper for an in-depth analysis of the thermal and energy challenges faced by modern high-density data centers, or get in touch with us to speak to our team about how to best approach data center design and construction.

Nueva llamada a la acción

Frequently Asked Questions About Data Center Design and Construction

What are the main stages of data center construction?

The main stages are the feasibility study and site selection, the conceptual design and capacity planning stage, the detailed engineering and infrastructure design stage, the procurement and equipment manufacturing stage, the construction and installation stage, the testing and commissioning stage and the handover and operational readiness stage.

How long does it take to design and build a data center?

There’s no single answer that is universally valid, because the answer depends on multiple factors that are project-specific. However, as a reference, a 20 MW data center construction project can last around 24 months if everything goes according to plan.

When should cooling infrastructure be planned?

The key cooling infrastructure choices should be made during the initial stages of a data center design and construction process.

What factors can delay data center construction?

Insufficient energy supply, extended equipment delivery times, contractor coordination challenges, design changes during the project’s late stages and complications in the commissioning stage are some of the key factors that tend to delay data center construction.

What is the role of commissioning in data center construction?

Data center commissioning is a structured quality assurance process that takes place before a data center goes live and aims to verify that all systems in the infrastructure are well-adjusted and ready to go into operation, achieving their expected performance standards.